[Traffic Control] Lighting System Renovation Work at Keelung Road Underpass
To provide the public with a brighter and more comfortable driving environment, the Parks and Street Lights (PSLO) announced that it will overhaul the dated lighting system along Keelung Road Underpass.
The project involves the removal of traditional lighting (1,597 units) and replacing them with power-saving LED versions (1,802 units). Other upgrades include new cables, electric facilities, automated lighting control system, and uninterruptible power supply (UPS).
Construction will be carried out during late night hours between 11 PM to 6 AM. The installation process requires a total of 180 work days and is slated for completion by November 30, 2020. PSLO reminds road users to follow the directions of onsite personnel and either slow down as they pass through the construction area or take the detour.
The agency explained that construction works will be divided into 4 major areas/phases to minimize the impact of power line switching and from the replacement of lighting devices upon tunnel traffic. Construction work will advance in the following order: the southbound central lane, the northbound central lane, the southbound mix-vehicle lane, and the northbound mix-vehicle lane. Signs, warning lights, and the presence of construction vehicles will alert passerby to pay attention and drive slowly. Details of traffic control are listed below.
Direction Scope Date Time Detours Songren Rd. To Xinyi Rd.(Southbound) Central Lane(Long Tunnel) 2020/06/01~2020/07/03 23:00~06:00
Songren Rd. To Xinyi Rd.(Southbound) Mixed Lane(Short Tunnel) 2020/08/15~2020/10/15 23:00~06:00 Xinyi Rd. To Songren Rd.(Northbound) Central Lane(Long Tunnel) 2020/08/04~2020/10/22 23:00~06:00
Xinyi Rd. To Songren Rd.(Northbound) Mixed Lane(Short Tunnel) 2020/09/04~2020/11/04 23:00~06:00 Illumination Tests and Adjustments 2020/11/05~2020/11/30 23:00~06:00